Posted by clueless [201.202.24.222] on Saturday, May 30, 2015 at 13:39:22 :
mack concrete pump truck and mack mixer showed up on time and we poured the second floor of the 2nd phase of the hostel
which means i will be able to open the first floor real soon cuz the 2nd floor is the 1rst floor roof
which means i can soon start work on the 6x6
calculated the m3 exact