1949 Dodge Power Wagon and Operation Highball


[Follow Ups] [Post Followup] [Dodge Power Wagon Forum]


Posted by Joe Cimoch [172.68.65.237] on Tuesday, February 27, 2018 at 11:09:31 :

Nice Power Wagon on ebay in Pennsylvania with an interesting background.

According to the description, the Power Wagon was used in the Hungry Horse Dam project in Montana. I couldn't locate any vintage pictures for a Trisdale Construction Power Wagon, but the story about Operation Highball was an interesting read. Especially the way the trees were cleared.

"In May 1950, Wixson and Crowe, Inc. and J.H. Trisdale (“Wixson and Trisdale”), contracting companies from Redding, California, brought a new method of clearing previously-logged or burned areas to Hungry Horse, Montana. The companies had already wiped clean nearly 7,000 acres (about 2,800 hectares) in the same area by dragging a two-inch thick steel cable strung between two diesel tractors through the forest, snapping or uprooting any trees caught in its path.

This worked very well in areas which had been burned, where the ground between the trees was relatively clear. However, in areas where loggers had already come through to cut “merchantable timber,” the cable, which could be as much as 200 feet long, tended to snag on stumps. The solution? A hollow steel ball eight feet in diameter and weighing four and a half tons, attached to the cable halfway between the two tractors. The ball not only held the cable above those perilous stumps, it also kept it from slipping off of the thinner, more flexible trees that the cable alone might not be able to fell.

The new method, nicknamed “Operation Highball,” worked so well that two tractors, 100 feet apart, could clear an average of 100 acres in eight hours. By adding winches to the tractors, and extending the cables to 900 feet, Wixson and Trisdale made it possible to loop 1,800 feet of a one and a quarter inch cable around a large stand of timber, then tighten the noose and drag the cable and ball through the trees trapped inside the circle. The downed trees were then scraped off the ground and stacked into burn piles by DC-8 tractors fitted with huge steel rakes. Trisdale, apparently never satisfied with off-the-shelf technology, even welded two of the DC-8s together and attached a 21-foot rake to his new “DC-16.” By September 1952, the firms had cleared a total of 14,695 acres (nearly 6,000 hectares).

Wixson and Trisdale were not doing this just for fun – they’d been hired by the United States Bureau of Reclamation to strip thousands of acres (much of it owned by the United States Forest Service) in preparation for the construction of Hungry Horse Dam. Wooded areas have to be cleared before they can be transformed into reservoirs, lest dead branches and rotting trees float to the surface and clog the dam intakes. While Wixson, Trisdale and other contractors busied themselves clearing the forest, others were pouring concrete and digging out tunnels. General-Shea-Morrison, the Seattle-based company chosen to build the dam, set up a construction camp with houses, dormitories, stores, a hospital and a schoolhouse. They also bridged the canyon and supplied the dam site with a blacksmith shop, machine shop, compressor house, and string of floodlights, so that they could work throughout the night."

Link to Popular Mechanics article (story on page 90) https://goo.gl/HZV5pm





Follow Ups:



Post a Followup

Name:
E-Mail:
Subject:
Message:
Optional Link
URL:
Title:
Optional Image Link
URL:


(1) Type your Message (2) Load New Code (3) Type new code into box. (4) Click "Post Message" button